Bangalore Agenda Task Force |
BATF Priority
Works... |
Desilting and emergent
repairs for the storm water drains from Sankey Tank to Sujatha talkies from Ch: 0 to 3450
m
Desilting and emergent
repairs for the storm water drains from Sujatha Talkies to Magadi Road from Ch: 3545 to
4870 m.
|
Tenders for the above works will be invited by 20-03-2000 after
scrutinizing the estimates and tender documents. As per the program drawn, the consultants
are to submit the balance estimates by 10-04-2000 and work orders will be issued for all
the works before 15-04-2000. The duration of contract is 45 days and accordingly all the
works are to be completed before 31-05-2000. |
3. Corporate co-ordinate works: |
The consultant for the above four road works has been identified and work
of preparation of estimate has been entrusted. The estimate received from the consultants
are scrutinized and are sent for certain modifications in the design and provisions made.
After receipt of tender estimates for the above works will be floated by 25-03-2000 and
the work orders will be issued during the second week of April 2000. All the above works
will be completed before 30-06-2000. |